Yangzhou Tianshun Pipeline Technology Co., Ltd., founded in 2012, is an integrated industry and trade enterprise focusing on R&D and manufacturing of pipeline support products. Over the past 14 years, we have served power, petrochemical and energy projects in more than 40 countries around the world, and won long-term trust from customers with stable product quality. The Heavy Duty Constant Spring Hanger is our flagship product developed for large-load and high-requirement working conditions. It has been systematically strengthened in materials, structure and technology to provide reliable guarantee for the safe operation of pipelines under extreme working conditions.

▶ Large-diameter thick-walled pipelines: Above DN600, wall thickness over 20mm
▶ Heavy-weight pipeline systems: Load per lifting point over 200kN, some over 500kN
▶ High-temperature and high-pressure main pipelines: Power plant main steam, high-temperature process pipelines of refining units
▶ Long-span pipelines: Large-span pipe sections in pipe galleries with large concentrated loads
▶ Shell deformation and cracking: Load exceeds structural bearing limit
▶ Insufficient spring stiffness: Excessive compression, loss of constant force characteristics
▶ Pin shear failure: Insufficient strength of connecting parts
▶ Suspension rod tensile deformation: Small diameter rod, overloading extension
The Heavy Duty Constant Spring Hanger is a reinforced product specially developed for such working conditions, with systematic strengthening from all dimensions of materials, structure and technology.
According to industry statistics, heavy duty working conditions account for more than 60% of pipeline support failure accidents:
Problem: Adopted ordinary constant force hanger, load per lifting point 280kNConsequence: Shell side plate cracked after 3 years of operation, pipeline sank 120mmLoss: 15 days of shutdown maintenance, direct loss over 10 million RMB
Problem: Hanger pin diameter was too small, strength decreased at high temperatureConsequence: Pin shear fracture, pipeline fell, causing medium leakageLesson: Heavy duty hangers must be calculated for strength separately according to actual working conditions
Problem: Material embrittlement at low temperature, ordinary Q235 shell crackedConsequence: Pipeline displacement out of control, cold box interface flange leakageImprovement: Heavy duty hangers adopt low-temperature toughness materials
In 14 years of industry experience, Yangzhou Tianshun Pipeline Technology has handled many similar heavy duty support failure transformation projects, and deeply understands the particularity and risks of heavy duty working conditions.
| Constant Spring Hanger Spec Table | Example |
| Model / Series | PH, LH, CA, CS, TH |
| Load Capacity (Operating) | 0.1 kN - 500 kN |
| Total Travel | 50mm, 100mm, 200mm, 400mm |
| Actual Travel | Up to 600mm |
| Load Deviation (Tolerance) | ±5% (Standard) / ±3% (High Prec.) |
| Installation Position | Horizontal / Vertical |
| Housing Finish | Hot Dip Galvanized / Epoxy |
| Operating Temp. | -20°C to +80°C (Ambient) |
| Spring Coil Material | 60Si2Mn / 50CrVA |
| Load Adjustment Range | ±10% (Field Adjusting) |
Shell adopts Q345B low-alloy high-strength steel, yield strength increased by 40%
Side plate thickness increased by 50%, whole plate cutting without splicing welds
Bottom reinforcing rib plate design to disperse concentrated stress
Pin adopts 40Cr alloy structural steel, quenched and tempered, strength increased by 80%
Pin diameter designed with 5 times safety factor of maximum load
Self-lubricating bushing adopted to reduce friction and improve constancy
2-4 sets of springs in parallel for large loads, single spring load controlled within reasonable range
Spring group synchronous compression design to avoid eccentric load
Each spring tested separately, matching deviation ≤2%
Lever arm cross-section enlarged, bending modulus increased by 100%
Thickened lining plate at fulcrum to prevent local crushing
Cam surface high-frequency quenched, hardness above HRC45, wear resistance life increased by 3 times
Key hole positions processed by CNC, position accuracy ±0.1mm
Lever moment ratio error controlled within ±1%
Spring compression accurately set, cold load deviation ≤3%
Main load-bearing welds adopt full penetration welding process
100% ultrasonic testing, meeting JB/T 4730 Grade II requirements
Post-weld stress relief treatment to eliminate welding residual stress
Upper and lower mechanical limits set to prevent over-stroke damage
Overload protection device, triggering warning under abnormal load
Displacement locking device to protect springs during installation and transportation
The following are measured data (300kN load, 200mm displacement working condition):
|
Stroke Position |
Ordinary Constant Force Hanger Load |
Heavy Duty Constant Spring Hanger Load |
National Standard Allowable Deviation |
|
0% (Cold state) |
282kN (-6.0%) |
294kN (-2.0%) |
±6% |
|
25% |
285kN (-5.0%) |
297kN (-1.0%) |
±6% |
|
50% (Middle) |
300kN (0%) |
300kN (0%) |
±6% |
|
75% |
318kN (+6.0%) |
306kN (+2.0%) |
±6% |
|
100% (Hot state) |
321kN (+7.0%) |
309kN (+3.0%) |
±6% |
|
Maximum deviation |
7.0% (Exceeding standard) |
3.0% (Far better than national standard) |
6% |
The full stroke load deviation of Heavy Duty Constant Spring Hanger is controlled within ±4%, far better than national standard requirements, effectively protecting the safety of pipelines and equipment.
Each Heavy Duty Constant Spring Hanger must complete the following verification before delivery:
Material certificate verification of steel plates and round bars
Spring steel hardness and composition re-inspection
Welding material compatibility verification
CMM inspection of CNC machining dimensions
Weld UT testing
Spring group load-displacement curve test
100% full stroke loading test, recording 20 measuring point data
Constancy calculation, rework for unqualified products
Locking device and limit device function test
Displacement indicator calibration
Material quality certification documents
Weld inspection report
Spring test report
Complete machine load-displacement test curve
Product qualification certificate and installation manual
|
Industry |
Application Scenarios |
Typical Load Range |
|
Power Industry |
Main steam and reheat steam pipelines of supercritical/ultra-supercritical units |
200kN ~ 800kN |
|
Petrochemical |
Hydroprocessing reactor outlets, large heating furnace inlet and outlet pipelines |
150kN ~ 600kN |
|
LNG Terminals |
Cold box inlets and outlets, large low-temperature process pipelines |
100kN ~ 500kN |
|
Long-Distance Pipelines |
Large-span pipe sections, concentrated load pipelines in valve chambers |
100kN ~ 400kN |
|
Nuclear Power |
Conventional island main steam, water supply system pipelines |
200kN ~ 700kN |
|
Metallurgy |
Blast furnace hot air pipelines, large waste heat boiler pipelines |
150kN ~ 500kN |
Exclusive Service Process for Heavy Duty Projects
1.Technical docking: Professional engineers dock with pipeline stress analysts to confirm load, displacement and space requirements
2.Scheme design: Provide customized design schemes for special space constraints
3.Drawing confirmation: Provide detailed assembly drawings and load tables, signed and confirmed by both parties
4.Production tracking: Provide weekly production progress photos for major projects
5.Factory acceptance: Customers or third parties can be invited to witness tests at the factory
6.On-site service: Provide installation guidance, on-site technical support if necessary
7.Operation tracking: Return visit 6 months after commissioning to understand operation status
▶ Delivered more than 500 sets of heavy duty constant force hangers, maximum single unit load 800kN
▶ All heavy duty products provide 3-year quality warranty
▶ Provide solutions for any quality problems during operation within 48 hours
▶ Lifetime technical consultation and spare parts supply
Heavy Duty Constant Spring Hanger is a reliable guarantee for the safe operation of heavy duty pipeline systems. With 14 years of focus, we deeply understand that heavy duty working conditions allow no mistakes. Each product has undergone strict testing to ensure stable operation under extreme working conditions.
Address
No.115 Yunhe North Road, Yangzhou City.Shuzhou, China
Tel
If you have any enquiry about quotation or cooperation, please feel free to email us at jsts2021@yeah.net or use the following inquiry form.Our sales representative will contact you within 24 hours. Thank you for your interest in our products.
Copyright © 2026 Yangzhou Tianshun Pipeline Technology Co., Ltd. All Rights Reserved.
